You are the project manager of TRT project. During execution phase of your project, Rick, a team member, complains that other team members are isolating him and this isolation is bothering him.

Which of the following is not a recommended step in order to resolve the issue?


A.

Apply team building measures to improve the team's effectiveness.


B.

Get more feed back from Rick.


C.

Get feedback on Rick from other team members.


D.

Shift Rick to another project.