GCPM Exam Topic 2 Question 13 Discussion:
Question #: 13
Topic #: 2

Which of the following processes is described in the statement below?

"It is the process of identifying the specific actions to be performed to produce the project deliverables."


A.

Define Activities


B.

Define Scope


C.

Sequence Activities


D.

Create WBS