New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

GIAC Certified Project Manager Certification Practice Test GCPM Question # 13 Topic 2 Discussion

GIAC Certified Project Manager Certification Practice Test GCPM Question # 13 Topic 2 Discussion

GCPM Exam Topic 2 Question 13 Discussion:
Question #: 13
Topic #: 2

Which of the following processes is described in the statement below?

"It is the process of identifying the specific actions to be performed to produce the project deliverables."


A.

Define Activities


B.

Define Scope


C.

Sequence Activities


D.

Create WBS


Get Premium GCPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.