Pass the FIDIC Contract Manager CCM Questions and answers with CertsForce

Viewing page 2 out of 3 pages
Viewing questions 11-20 out of questions
Questions # 11:

Before applying the procurement process of any FIDIC Book, the Employer should always check if there are local procurement rules that also apply. Which one of these responses is correct?

Options:

A.

No, because the FIDIC procurement process is universal.


B.

No, because Employers never have specific procurement rules.


C.

Yes, based on the law system, internal governance or type of Employer additional procurement rules can apply.


D.

Yes, but this is only applicable for public entities like governments. If the Employer is a private organisation (like a company), they are free to procure how they want.


Expert Solution
Questions # 12:

Under the FIDIC Red Book (edition 1999), as part of the Contractor submission of Statement, any amount to be deducted for retention, will be calculated by applying the percentage of retention stated in the Appendix to Tender to the total of: (two correct answers apply)

Choose all of the correct answers (multiple possibilities).

Options:

A.

The estimated contract value of the Works executed.


B.

Any amounts to be added and/or deducted for the advance payment and repayments under Sub-Clause 14.2.


C.

Any amounts to be added and deducted for changes in legislation and changes in cost.


D.

Any amounts to be added and deducted for Plant and Materials in accordance with Sub-Clause 14.5.


Expert Solution
Questions # 13:

In which one of the following circumstances is it recommended to select the Contractor after a two-stage procurement procedure (pre-qualification + tender procedure)?

Options:

A.

When the works are simple and of short duration.


B.

When there is a limited number of capable experienced contractors available and ready to take part in the procurement.


C.

In case of large scale works, where there are several companies likely to have an interest in submitting an offer.


D.

If there is international financing for the project, it is always necessary to conduct a two-stage procurement procedure.


Expert Solution
Questions # 14:

A new important feature of the FIDIC Yellow and Silver Books (edition 2017) is the inclusion of the default position that the Works or relevant part of the Works designed by the Contractor shall be fit for their ordinary purposes. Is this statement true or false?

Options:

A.

True


B.

False


Expert Solution
Questions # 15:

You are the Contract Manager of the Engineer in a condominium project under FIDIC Yellow Book (edition 2017), with Time for Completion of 5 months.

The Contractor received a Letter of Acceptance on 1 May 2022. The Contract Agreement was signed on 1 June 2022. The Contract Agreement states that the Commencement Date shall be notified by the Engineer, but it shall be no later than 14 days after the signing of the Contract Agreement, subject to the issuance of the construction permit.

1 July 2022 is the first day the Engineer was at Site. On the same day, the Engineer issued a Notice to the Contractor that the Commencement Date shall be 15 July 2022. However, the construction permit was issued only on 1 August 2022.

The Project was completed on 1 December 2022. After completion, the Employer submitted a claim for Delay Damages. Following consultations, the Parties could not reach agreement on the Commencement Date.

What is the correct Commencement Date?

Options:

A.

12 June 2022


B.

15 June 2022


C.

15 July 2022


D.

1 August 2022


Expert Solution
Questions # 16:

Which of the following form a Contractor's entitlement, in case the Contractor does not receive an interim payment within the allocated contractual deadline for payment? (2 correct answers apply)

Choose all of the correct answers (multiple possibilities).

Options:

A.

Right after the expiry of the payment deadline, the Contractor may terminate the contract.


B.

If the payment is not made within the time period required, after the expiry of such period, from the next day onwards, the Contractor is entitled to suspend all his/her activities on Site.


C.

In case the Employer paid the Contractor late, the Contractor becomes entitled to receive financing charges applying the % included in the Contract Data (if this is not stated, then applying the percentage as included under the corresponding Sub-Clause).


D.

The Contractor is entitled to suspend the works or reduce the rate of progress of the work, after giving a due Notice (21 days) about this intention.


E.

Beyond receiving the financing charges, the Contractor has no further entitlements in such a case.


Expert Solution
Questions # 17:

Under the FIDIC Red and Yellow Books (edition 1999), which two of the following statements are correct regarding the issuance of Interim Payment by the Engineer?

(Choose all correct answers — multiple possibilities)

Options:

A.

The Employer is bound by the Certificate issued by the Engineer, and must make payment in full, except for any compensation arising from any claim which the Employer may have against the Contractor.


B.

The Employer is not bound by the Certificate issued by the Engineer.


C.

The Employer is bound by the Certificate issued by the Engineer and must make payment in full, irrespective of any entitlement to compensation arising from any claim which the Employer may have against the Contractor.


D.

If the Employer considers itself entitled to claim against the Contractor, notice and particulars must first be submitted under Sub-Clause 2.5. The Employer's entitlement is then to be agreed or determined by the Engineer, and then, incorporated as a deduction in a Payment Certificate.


Expert Solution
Questions # 18:

The details of all the matters that have been clarified and agreed between the Employer and tenderers during the tender stage are recorded by, for instance, a memorandum of understanding. The Employer may award the contract to the tenderer through a letter of formal acceptance, signed by the Employer. This process is in compliance with which one of the following Golden Principles (GP's)?

Options:

A.

GP 3


B.

GP 1


C.

GP 2


D.

GPA


Expert Solution
Questions # 19:

You are the Contract Manager in a highway project using FIDIC Red Book (edition 1999). You work for the Employer– a highway management agency. During the tender period, you are informed of a specific Commencement Date required by the directors of the agency. Which two of the following approaches to inform the tenderers of this date are clearly and unambiguously drafted?

Choose all of the correct answers (multiple possibilities).

Options:

A.

Specify Commencement Date in the Minutes of Meeting of Contract Negotiation.


B.

Specify Commencement Date in the Contract Agreement.


C.

Specify Commencement Date in the Particular Conditions.


D.

Inform the Commencement Date to the tenderers by email, and attach that email in the list of Contract Documents.


Expert Solution
Questions # 20:

Under the FIDIC Red Book (edition 2017), if the Contractor fails to comply with Site clearance obligation, what two options does the Employer have?

Choose all of the correct answers (multiple possibilities)

Options:

A.

The Employer may sell or otherwise dispose any remaining items and reinstate the Site at the Contractor's Cost.


B.

The Engineer cannot sell or otherwise dispose any remaining items and reinstate the Site at the Contractor's Cost.


C.

The Employer is entitled to the cost of reinstating, clearing the Site and disposal cost to the extent they exceed the money received from selling the remaining Contractor's items on the Site.


D.

The Employer cannot reinstate and clear the Site and dispose the remaining Contractor's items on the Site if the Contractor fails, as this is the Contractor's obligation.


Expert Solution
Viewing page 2 out of 3 pages
Viewing questions 11-20 out of questions