Questions # 31:

Which individual occupant lighting control meets the requirements of Indoor Environmental Quality Credit, Interior Lighting?

Options:

A.

Two Level (on, off)


B.

Three Level (on, 25%, off)


C.

Three Level (on, 50%, off)


D.

Three Level (on, 75%, off)


Expert Solution
Questions # 32:

A LEED Building Design and Construction: New Construction office building's HVAC system includes hot water from a central utility plant. The central utility plant is owned and operated by a management company. The office pays a flat fee for hot water, included as part of the lease. The management company does not meter or invoice for actual hot water consumption. For the project to meet the requirements for Energy and Atmosphere Prerequisite, Building-Level

Energy Metering, an energy meter must be installed for

Options:

A.

natural gas


B.

hot water at the main service point


C.

nothing, because the flat fee is included as part of the lease


D.

nothing, because the energy source is outside of the project's scope


Expert Solution
Questions # 33:

Where must a building's no-smoking signage be posted?

Options:

A.

Within 10 ft. (3 m) of all building entrances


B.

Within 10 ft. (3 m) of the main building entrance(s)


C.

Within 25 ft. (8 m) of all building entrances


D.

Within 25 ft. (8 m) of the main building entrance(s)


Expert Solution
Questions # 34:

In the Indoor Environmental Quality Credit, Low-Emitting Materials, what types of products need to be evaluated for

both Volatile Organic Compound (VOC) content of the material and VOC emissions of the material?

Options:

A.

Flooring


B.

Furniture


C.

Composite wood


D.

Wet applied products


Expert Solution
Questions # 35:

Which of the following is a leadership extraction practice that rewards projects for choosing materials with closed-loop recycling and take-back programs in LEED?

Options:

A.

Material reuse


B.

Bio-based elements


C.

Extended producer responsibility


D.

Forest Stewardship Council (FSC) wood products


Expert Solution
Questions # 36:

A downtown office building is unable to construct dedicated parking for its occupants. However, the building developer has partnered with a parking garage to offer discounted parking for its occupants. If the discounted parking rate is $450 per month, how much must the rate be for green vehicles for the building to receive one point for Location and Transportation Credit, Green Vehicles?

Options:

A.

$90


B.

$225


C.

$360


D.

$405


Expert Solution
Questions # 37:

For a bicycle network to demonstrate compliance with Location and Transportation Credit, Bicycle Facilities, the bicycle network must connect to

Options:

A.

five bicycle trails


B.

at least eight diverse uses


C.

a restaurant, a grocery shop, a post office and two bus lines


D.

a rapid transit stop that is within 3 mi. (5 km) biking distance of the project boundary


Expert Solution
Questions # 38:

When the LEED AP is applying the Integrative Process to a Building Design and Construction project, when should the Owner’s Project Requirements (OPR) be created and updated?

Options:

A.

Prior to beginning design and are generally not updated


B.

Once the project design is completed and edited throughout the project


C.

During predesign and are edited throughout the project


D.

After the design is completed and are generally not updated


Expert Solution
Questions # 39:

A building owner is considering the installation of a solar thermal panel on the roof of the building. The initial cost of the system is higher than a conventional natural gas system. Which of the following is true to make the renewable energy option economically feasible?

Options:

A.

Utility cost savings over the lifetime of the system must offset the higher initial cost


B.

Higher initial cost must exceed the cost of the utility over the lifetime of the system


C.

Higher initial cost must exceed the savings on the utility cost over the lifetime of the system


D.

Utility cost savings over the lifetime of the system must be lower than the higher initial cost of the system


Expert Solution
Questions # 40:

When calculating the reverberation time of a room, which of the following pieces of information is least relevant?

Options:

A.

Height and width of room


B.

Noise reduction coefficient of the ceiling surface


C.

Sound absorption coefficient of the floor surface


D.

Operating sound level of nearest HVAC equipment


Expert Solution