The table below outlines a few Scrum roles that play an important role in business justification and their responsibilities. Choose the option that correctly matches each role to its action.
Scrum Roles
I. Sponsor
II. Scrum Guidance Body
III. Customers and Users
IV. Scrum Master
Actions
a. Facilitates creation of the project's deliverables; manages risks, changes, and impediments.
b. Defines the prioritized list of requirements and User Stories in the Prioritized Product Backlog.
c. Provides funding for the project.
d. Provides guidelines and recommendations related to business justification techniques and other aspects.
As Scrum Master, you and the Product Manager are evaluating possible risks that might affect the project's outcome. You must categorize and organize the identified risks based on their similarities. Which of the Risk Identification Techniques listed below will you employ?
Which of the following meetings is not Time-boxed and can be conducted in a virtual environment?
The Product Owner on a project to manufacture components for engines used in submarines received feedback from the customer after the first release that there were some defects in the product, but that the product could be released despite the defects. However, if there is an increase in the number of defects, the deliverables would be rejected. This is an example of:
Suppose you are a Scrum Master on a project to design a metro rail system for a city. It has been brought to your attention that the Product Owner wants to change the Acceptance Criteria for one of the User Stories committed to the current Sprint because the customer has changed a critical business requirement. Which one of the following statements presents the best solution for such a situation?
As a Scrum Master, you should understand what a risk is and how to handle it. Which of the following claims about how risk is defined in the Scrum framework is FALSE?
One of the responsibilities of the Chief Scrum Master is to be a part of the Retrospect Project Meeting. Which of the following statements about the Retrospect Project Meeting is/are true?
I. This meeting helps determine ways in which the team should communicate and maintain the knowledge base.
II. During this meeting, positives, negatives, and potential opportunities for improvement are discussed.
III. This meeting is Time-boxed and may be conducted in person or in a virtual format.
IV. The lessons learned during this meeting are documented.
The Scrum Master should ensure the following in order for the Product Owner to successfully deploy the product release as part of the Ship Deliverables process:
Clara is a Scrum Master on a project that involves offshore oil drilling. The Product Owner on her project has identified that there is a probability of getting new orders in the future, which might depend on the performance of the project. How would this risk be labelled?
Which of the following are the questions that are generally answered during the Scrum of Scrums Meeting?
I. What has my team been working on since the last meeting?
II. What will my team do until the next meeting?
III. What were other teams counting on our team to finish that remains undone?
IV. What is our team planning on doing that might affect other teams?