Question #: 8
Topic #: 1

The Scrum Master should ensure the following in order for the Product Owner to successfully deploy the product release as part of the Ship Deliverables process:


A.

The Scrum Team creates Deliverables as agreed upon.


B.

The Release Plan and Prioritized Product Backlog are updated.


C.

The Scrum Team creates the Release Planning Schedule.


D.

The Scrum Team accepts/rejects the deliverables during the Demonstrate and Validate Sprint process.