Question #: 9
Topic #: 1

Clara is a Scrum Master on a project that involves offshore oil drilling. The Product Owner on her project has identified that there is a probability of getting new orders in the future, which might depend on the performance of the project. How would this risk be labelled?


A.

As a Threat


B.

As an Issue


C.

As a Weakness


D.

As an Opportunity