SMC Exam Topic 1 Question 2 Discussion:
Question #: 2
Topic #: 1

As Scrum Master, you and the Product Manager are evaluating possible risks that might affect the project's outcome. You must categorize and organize the identified risks based on their similarities. Which of the Risk Identification Techniques listed below will you employ?


A.

Risk Checklists


B.

Risk Prompt Lists


C.

Brainstorming


D.

Risk Breakdown Structure