Scrum Master Certified (SMC) SMC Question # 5 Topic 1 Discussion

Scrum Master Certified (SMC) SMC Question # 5 Topic 1 Discussion

SMC Exam Topic 1 Question 5 Discussion:
Question #: 5
Topic #: 1

Suppose you are a Scrum Master on a project to design a metro rail system for a city. It has been brought to your attention that the Product Owner wants to change the Acceptance Criteria for one of the User Stories committed to the current Sprint because the customer has changed a critical business requirement. Which one of the following statements presents the best solution for such a situation?


A.

You should direct the Scrum Team to stop working on the current Sprint Backlog and start working on the latest business requirements.


B.

The Product Owner should add this requirement to the overall Prioritized Product Backlog, and the team would work on it in a future Sprint.


C.

You should tell the Product Owner to inform the stakeholders that this business requirement cannot be worked on because the Scrum Team has no bandwidth in the current Sprint.


D.

The Product Owner should cancel the current Sprint and start planning a new Sprint for the team to develop the deliverable according to the latest business requirement.