A project team identifies a number of technical challenges with features in the next sprint What should they do?
During a retrospective, the team agrees that they have limited competence in using a newly introduced tool. What should the team do?
Team A is working on the second sprint of a product release Team B which is an interdependent team located on the same floor, requires extensive and frequent information to complete its sprint goal.
What should the agile team lead do?
A development team determined the first release of a product should focus on delivering a minimally viable version of the solution. What is the most important reason the team decided to do this?
An agile team is working on the first sprint, and have already planned the second and third sprints. However, market conditions now require a change to the features. What should the product owner do?
Daily coordination meeting attendance has been declining recently. Those who attend have little to contribute outside of what they are currently working on. The project manager met with the team to remind them of the importance of regular, face-to-face communication. The project team feels the daily coordination meetings are not adding value.
What should the project manager do?
When a team member encounters an issue in an agile environment, what should they do?
During an executive review, a scrum master uses a burndown chart to demonstrate team deliverables through time. The scrum master declared that velocity increased from 27 to 35 over the last 3 sprints, but one of the executives asks to clarify the importance of these metrics.
How should the scrum master respond?
An agile coach is working on a software development project. Their team is approaching the sprint deadline, but their client is requesting to include additional features that will bring added value.
What should the agile coach do to address this requirement?
An agile coach is working on a software development project. Their team is approaching the sprint deadline, but their client is requesting to include additional features that will bring added value.
What should the agile coach do to address this requirement?
The team is in the middle of an iteration and there is an urgent request for a small change to be introduced to the committed scope Unless this change is accepted, there is no value to the customers during this iteration.
What must the agile practitioner do?