Question #: 35
Topic #: 4

An agile team is working on the first sprint, and have already planned the second and third sprints. However, market conditions now require a change to the features. What should the product owner do?


A.

Communicate the importance of the business need to the team and refine the product backlog.


B.

Ask the team to discuss the changes to the features with the customer.


C.

Meet with the agile team lead to prioritize the requirements.


D.

Discuss and prioritize the requirements with the team.