Questions # 16:

You have been with the organization; you constantly hear rumours about a certain CAPM failing to live up to the CAPM Code. What you should do?

Options:

A.

You can gather as much information as you can before proceeding


B.

Confront the person immediately


C.

Ignore the rumours


D.

^ass the rumours along


Expert Solution
Questions # 17:

If a project with a CPI of 1.2, what you tell?

Options:

A.

The project is consuming fewer resources than anticipated


B.

The project is using fewer resources than anticipated.


C.

The project is falling behind.


D.

The project is running ahead of schedule.


Expert Solution
Questions # 18:

Which of the following are the inputs of Define Scope?

Options:

A.

Requirements document created in collect requirements process


B.

Project files from previous projects


C.

Project Charter


D.

Al1 of the above


Expert Solution
Questions # 19:

When you are developing the estimates for project, you choose in a mathematical model to predict estimate. What type of estimation method are you using?

Options:

A.

Parametric estimating


B.

Bottom-up estimating


C.

Top-down estimating


D.

Analogous estimating


Expert Solution
Questions # 20:

Administrative closure is the process that ________.

Options:

A.

Closes all activities pertaining to a specific project


B.

Collects user acceptance of the project product or service


C.

Includes all the activities needed to validate the project products and services


D.

Al1 of the above


Expert Solution
Questions # 21:

Who gives project acceptance?

Options:

A.

Sponsor


B.

Customer


C.

Project Manager


D.

Team Lead


Expert Solution
Questions # 22:

What is the lowest level in a work breakdown structure?

Options:

A.

Project task


B.

w°rl< package


C.

sow


D.

None


Expert Solution
Questions # 23:

You are project manager of a project and as part of the team acquisition process; you hire a new employee and assigns him to your project team. According to Maslow's hierarchy of needs, what needs level he most likely is at?

Options:

A.

Social need


B.

Physical need


C.

Safety and security


D.

Security


Expert Solution
Questions # 24:

Customer formally accepts the deliverables of each project phase. This process is known as ________.

Options:

A.

Verify Scope


B.

Quality Assurance


C.

Quality Control


D.

Quality Measurement


Expert Solution
Questions # 25:

In PMBOK, the buyer is ________ to the project team.

Options:

A.

Internal


B.

External


C.

Outside


D.

Assigned


Expert Solution
Questions # 26:

Your company create software products, and introducing a new product. To determine the characteristics and features of the new product line, you will have to perform ________.

Options:

A.

Progressive elaboration


B.

Stake holder's review


C.

p'an project life cycle


D.

Fast backing


Expert Solution
Questions # 27:

Information should be communicated to __________.

Options:

A.

Everyone in the communication plan


B.

Everyone on the team


C.

Sponsor


D.

Team 'eacl


Expert Solution
Questions # 28:

A Risk Register is a part of the ________.

Options:

A.

Project Scope Statement


B.

Project Management plan


C.

Project Scheduling plan


D.

Project Charter


Expert Solution
Questions # 29:

When the version control numbers should change?

Options:

A.

Any change occurs


B.

Major changes are made


C.

Any change related to scope only


D.

Only if minor changes are made


Expert Solution
Questions # 30:

Which is the most risky phase of a project?

Options:

A.

Planning


B.

Closing


C.

Execution


D.

Control


Expert Solution