PMI Certified Associate in Project Management (CAPM) Certification PMI-002 Question # 22 Topic 3 Discussion

PMI Certified Associate in Project Management (CAPM) Certification PMI-002 Question # 22 Topic 3 Discussion

PMI-002 Exam Topic 3 Question 22 Discussion:
Question #: 22
Topic #: 3

What is the lowest level in a work breakdown structure?


A.

Project task


B.

w°rl< package


C.

sow


D.

None


Get Premium PMI-002 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.