PMI Certified Associate in Project Management (CAPM) Certification PMI-002 Question # 17 Topic 2 Discussion

PMI Certified Associate in Project Management (CAPM) Certification PMI-002 Question # 17 Topic 2 Discussion

PMI-002 Exam Topic 2 Question 17 Discussion:
Question #: 17
Topic #: 2

If a project with a CPI of 1.2, what you tell?


A.

The project is consuming fewer resources than anticipated


B.

The project is using fewer resources than anticipated.


C.

The project is falling behind.


D.

The project is running ahead of schedule.


Get Premium PMI-002 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.