Questions # 61:

Complete final contract performance reporting and verify product is done in _______.

Options:

A.

Plan Procurements


B.

Conduct Procurements


C.

Administer Procurements


D.

Close Procurements


Expert Solution
Questions # 62:

You are the project manager of a project. The project plan has been developed. A project end date has been established. The customer later requesters additional work to be included in the project, but will not renegotiate the end date. Cost is not a factor. What should the project team do immediately?

Options:

A.

Invoke the change control process


B.

Initiate contingency plans


C.

Modify the original project scope to include the additional work


D.

Commit to original project scope and open a new project to handle additional work


Expert Solution
Questions # 63:

The major project scope management processes include:

Options:

A.

Change order control


B.

Initiation


C.

Program evaluation


D.

Scope validation


Expert Solution
Questions # 64:

You are the controller on your project. Your project manager has requested that you provide him with a forecast of project costs for the next 12 months. He needs this information to determine if the budget should be increased or decreased on this major construction project. In addition to the usual information sources, which of the following should you also consider?

Options:

A.

Cost estimates from similar projects


B.

The WBS


C.

Long-range weather forecasts


D.

Existing change requests


Expert Solution
Questions # 65:

The items at the lowest level of the WBS are called __________.

Options:

A.

Code of accounts


B.

Subtasks


C.

Work packages


D.

Nodes


Expert Solution
Questions # 66:

A risk response which involves eliminating a threat is called

Options:

A.

Mitigation


B.

Deflection


C.

Avoidance


D.

Transfer


Expert Solution
Questions # 67:

Determining conformance with scope requirements is called _________.

Options:

A.

Quality Management


B.

Quality Assurance


C.

plan Quality


D.

Quality Control


Expert Solution
Questions # 68:

Which of the following is true concerning the evaluation criteria?

Options:

A.

Can often be found in procurement documents


B.

Can be objective or subjective


C.

Used to rate or score proposals


D.

All of the above


Expert Solution
Questions # 69:

Which of the following statement is true about Quality control?

Options:

A.

Monitoring specific project results to determine If they comply with relevant quality standards


B.

Evaluating overall project performance on a regular basis


C.

Taking action to increase the effectiveness and efficiency of the project


D.

Identifying which quality standards are relevant to the project


Expert Solution
Questions # 70:

Team motivation, problem resolution, and space verification occur during which process?

Options:

A.

Initiation


B.

Planning


C.

Execution


D.

Close


Expert Solution
Questions # 71:

A relatively small number of causes typically produce a majority of the problems and defects is a concept of ___________.

Options:

A.

Edward Deming


B.

phil'P Crosby


C.

Juian


D.

Pareto


Expert Solution
Questions # 72:

Which of the following are not functions of the project kick off meeting?

Options:

A.

Identifying project goals


B.

Obtaining commitment


C.

Presenting the project cost


D.

Introducing the stakeholders


Expert Solution
Questions # 73:

Which process involves Formal product acceptance and end of project?

Options:

A.

Executing processes


B.

Planning processes


C.

Controlling Processes


D.

Closing processes


Expert Solution
Questions # 74:

Which of the following statements concerning bottom up estimating is true?

Options:

A.

The cost and accuracy of bottom-up estimating is driven by the size of the individual work items


B.

Smaller work items increase both cost and accuracy


C.

Larger work items increase both cost and accuracy


D.

Both A and B are true


Expert Solution
Questions # 75:

A scope management plan describes __________.

Options:

A.

An assessment of the stability of the stakeholder environment


B.

A highly detailed approach to managing the work breakdown structure scope


C.

How the project scope will be managed and how scope changes will be integrated into the project


D.

The stakeholder's expectation on how changes will be identified and by what priority they will be addressed


Expert Solution