PMI Certified Associate in Project Management (CAPM) Certification PMI-002 Question # 69 Topic 7 Discussion

PMI Certified Associate in Project Management (CAPM) Certification PMI-002 Question # 69 Topic 7 Discussion

PMI-002 Exam Topic 7 Question 69 Discussion:
Question #: 69
Topic #: 7

Which of the following statement is true about Quality control?


A.

Monitoring specific project results to determine If they comply with relevant quality standards


B.

Evaluating overall project performance on a regular basis


C.

Taking action to increase the effectiveness and efficiency of the project


D.

Identifying which quality standards are relevant to the project