Questions # 51:

You have been seeing a high number of rejections of defect reports The developers are complaining that they do not understand what the problem is. even though they have been supplied with screenshots. You have checked a number of the 'problem' defect reports and have not found any information that is missing. The descriptions are very detailed and include all the necessary information in a long descriptive paragraph.

What change should you recommend that should help with the developer s problems?

Options:

A.

instruct your team to make all defects high priority so the developers have more urgency behind making the fixes


B.

With the problem reports highlight all the information and then walk through it with the developers so they see it is all there


C.

In addition to attaching the screenshots to the defect report, ask the testers to also email them to the developer


D.

Separate out the steps to reproduce the defect in the description so it is clearer for the developers and easier to find


Expert Solution
Questions # 52:

You have been looking at the actual vs expected defects in one high risk area of the software The actual is much higher than the expected value What should you do?

Options:

A.

Reassess the risk with a higher likelihood number


B.

Reassess the risk with a higher impact number


C.

Concentrate more testing in the area because the risk is clearly higher


D.

Concentrate less testing in the area because the defects are already found


Expert Solution
Questions # 53:

You are managing the testing for a bank card project. The testing was scheduled to take 10 weeks but by the time the software was developed only six weeks were available for testing Knowing there were a lot of risks with the software your team started testing activities early by overseeing code reviews, defining acceptance criteria by working with the users and by doing all lest creation prior to the code arriving

You are now three days away from the go-live date Your testing has mitigated all the high and medium risk items leaving only the low-risk elements unmitigated by testing You estimate it will take two weeks to manually test the low-risk elements At this point what should you do?

Options:

A.

Automate the testing of the untested elements to ensure they are covered


B.

Block the go-live and start testing the low-risk elements immediately


C.

Transfer the risk of the untested low-risk items to the help desk


D.

Select one of the low-risk elements and perform depth testing to assess the residual risk


Expert Solution
Questions # 54:

In what way is the operations team usually Involved In testing7

Options:

A.

To conduct operational acceptance testing


B.

To conduct user acceptance testing


C.

To conduct security testing


D.

To conduct end-to-end transactional testing


Expert Solution
Questions # 55:

When Is the metric for the percentage of requirements coverage defined?

Options:

A.

Test planning


B.

Test monitoring


C.

Test execution


D.

Test completion


Expert Solution
Questions # 56:

You are working on a project where the business part of the organization works traditionally with defined requirements, but the development team follows an Agile model Neither team plans to change their approach What is the proper name for this type of project approach''

Options:

A.

Sequential


B.

Hybrid as a transition to Agile


C.

Agile


D.

Hybrid as fit for purpose


Expert Solution
Questions # 57:

Your team has been assigned to a new project You have a mix of manual testers and automation engineers but everyone is currently doing manual testing. The development learn has alreadydecided to use DevOps as its approach but they have never used it before and are happy to take your input Unfortunately, about 50% of the development is completed already In the testing your team is doing they are finding that about 40% of the defects they catch are actually regressions caused by other changes

Given this information what should you do to help mitigate risk'?

Options:

A.

Review the policies regarding defect reporting and ensure your team is adding all the necessary information to each defect report


B.

Pivot part of the team from manual testing to test automation development to address the regression risk and implement better quality gates to reduce regressions


C.

Optimize the test environment to provide faster testing with more accurate test data and better testing tools to provide wider coverage


D.

Implement code reviews for the development team and require tester signoff before code can be released into the pipeline


Expert Solution
Questions # 58:

In an Agile project, when Is it acceptable lo not write a formal defect report when a defect is found''

Options:

A.

Never


B.

If the defect can be fixed in the same iteration in which it was found


C.

the defect can be fixed in a later hardening sprint


D.

If the defect must be fixed by another team


Expert Solution
Questions # 59:

You are working In an environment that is continually pushing process improvements down to the lest team You are skeptical that any of these have actually accomplished any improvement In fact you know that some of the changes have actually impaired progress

Given this information what step of the IDEAL model is missing?

Options:

A.

Diagnosing


B.

Establishing


C.

Acting


D.

Learning


Expert Solution
Questions # 60:

You have been asked to estimate the testing effort for an upgrade to a legacy product Your team did the testing on the last upgrade, and you have ascertained that this upgrade is about 10% bigger than the last one Given this information which estimation technique should you use to come up with the test effort number?

Options:

A.

Function points


B.

Extrapolation


C.

Planning poker


D.

Three-point estimation


Expert Solution