ISTQB Certified Tester Advanced Level Test Management (CTAL-TM) v3.0 CTAL-TM Question # 53 Topic 6 Discussion

ISTQB Certified Tester Advanced Level Test Management (CTAL-TM) v3.0 CTAL-TM Question # 53 Topic 6 Discussion

CTAL-TM Exam Topic 6 Question 53 Discussion:
Question #: 53
Topic #: 6

You are managing the testing for a bank card project. The testing was scheduled to take 10 weeks but by the time the software was developed only six weeks were available for testing Knowing there were a lot of risks with the software your team started testing activities early by overseeing code reviews, defining acceptance criteria by working with the users and by doing all lest creation prior to the code arriving

You are now three days away from the go-live date Your testing has mitigated all the high and medium risk items leaving only the low-risk elements unmitigated by testing You estimate it will take two weeks to manually test the low-risk elements At this point what should you do?


A.

Automate the testing of the untested elements to ensure they are covered


B.

Block the go-live and start testing the low-risk elements immediately


C.

Transfer the risk of the untested low-risk items to the help desk


D.

Select one of the low-risk elements and perform depth testing to assess the residual risk