Question #: 60
Topic #: 7

You have been asked to estimate the testing effort for an upgrade to a legacy product Your team did the testing on the last upgrade, and you have ascertained that this upgrade is about 10% bigger than the last one Given this information which estimation technique should you use to come up with the test effort number?


A.

Function points


B.

Extrapolation


C.

Planning poker


D.

Three-point estimation