Questions # 1:

If a stakeholder has high power in a business but isn’t interested in your procurement activity, what should be your management style for dealing with this stakeholder?

Options:

A.

Keep them satisfied – they have high power


B.

Keep them informed – they have high power


C.

Manage closely – they’re a key player


D.

Minimum effort is required as they’re not interested- do nothing


Questions # 2:

A category buyer, managing an outsourcing project, is aware of the commercially sensitive nature of the project and wishes to adopt an accommodating approach to managing conflict amongst key stakeholders. Is this the correct approach?

Options:

A.

No, as the category manager has a low concern for others and a low concern for themselves


B.

Yes, as the category manager has a high concern for others and a high concern for themselves


C.

No, as the category manager has a high concern for themselves and low concern for others


D.

Yes, as the category manager has a low concern for themselves but high concern for others


Questions # 3:

According to Michael Porter, what is procurement?

Options:

A.

a support activity which provides a source of competitive advantage


B.

a primary activity which provides a source of competitive activity


C.

a primary activity which provides value for money


D.

a secondary activity which provides value for money


Questions # 4:

Which of the following are Intellectual Property Rights that you would you encounter in procurement and supply contracts? Select THREE.

Options:

A.

Method Statements


B.

Risk Assessments


C.

Patents


D.

Copywrite


E.

Trademark


Questions # 5:

The CEO of a business has asked his procurement manager to source new machinery for the factory. This machinery will help create a new line of products which will give the company a competitive edge. The CEO is heavily invested in this procurement activity as profits have been lower than expected this year and this new line of products could help increase profitability. How should the procurement manager include the CEO in the procurement activity?

Options:

A.

It is important to keep the CEO informed of all decisions that are made


B.

It is important to keep the CEO satisfied as he runs the business


C.

The CEO is a key player- so it is important he is involved early in the process


D.

The CEO is a key player- so should be given regular updates on progress


Questions # 6:

A company's analysis shows that some of their products from a supplier fall into the 'strategic' segment of the supply positioning grid. They are meeting with the supplier with the intention that they enter into a partnership. The supplier views the company as 'core' to their business. Which one of the following factors would be most important in determining that a partnership agreement would be good for both companies?

Options:

A.

They have a high spend with the supplier


B.

They have a low spend with the supplier


C.

Their products are technically simple


D.

There are many suppliers in the market


Questions # 7:

A common reason attributed to many partnerships failing is ...

Options:

A.

A bad advertising campaign


B.

Not winning every contract they bid for


C.

No contract being in place


D.

Poor communication


Questions # 8:

Red Ltd and Blue Ltd have had a disagreement over a high value project they have been partnering on. They have been unable to resolve the issues inhouse and Red Ltd has suggested Mediation as an option. Is this a good option?

Options:

A.

Yes- mediation involves a neutral third party and gets both parties to attempt to reach a compromise


B.

Yes- mediation means the buyer and supplier agree to accept a third party’s decision which will solve the disagreement issues


C.

No- it would be better to solve the disagreement in-house


D.

No- mediation could have a negative impact on the companies’ reputation


Questions # 9:

Danny is procuring a new IT software, which he doesn’t know much about. He has done a bit of research on the internet but is still unsure how much he can expect to pay. What should be Danny’s next step?

Options:

A.

Issue a RFI


B.

Issue a RFQ


C.

Issue an ITT


D.

Issue an OJEU


Questions # 10:

When overcoming stakeholder resistance in a procurement-led project, which of the following groups would have the highest level of influence on other stakeholders?

Options:

A.

2 and 3 only


B.

1 and 4 only


C.

1 and 2 only


D.

3 and 4 only


Viewing page 1 out of 8 pages