Pass the CIMA CIMA Management E2 Questions and answers with CertsForce

Viewing page 5 out of 7 pages
Viewing questions 41-50 out of questions
Questions # 41:

In the model of the organisational iceberg, which of the following is NOT one of the hidden elements?

Options:

A.

Communication pattern


B.

Feelings


C.

Style


D.

Structure


Expert Solution
Questions # 42:

An experienced IT project manager provides the following advice about planning a new project:

 

"The project should start with a Requirements Analysis which should take 10 days.  When this is finished Detailed Design (10 days) and Interface studies (15 days) can start at the same time. As soon as they are both complete Prototyping can start (30 days).

 

Prototyping is the predecessor of both Implementation (10 days) and Data Conversion (20 days).

 

Go-Live is the final activity (5 days) and follows when Implementation and Data Conversion are both complete."

 

Using critical path analysis which statements are correct.

 

Select ALL that apply.

Options:

A.

The planned duration of the project is 80 days.


B.

The critical path runs through five activities.


C.

Data Conversion is non-critical and has float of 25 days.


D.

There are four non-critical activities.


Expert Solution
Questions # 43:

P is an experienced engineer and project manager that has just been appointed to manage a complex multi-million pound engineering project. It is the start-up stage of the project and nothing at all has been done so far except for the design work. No other team members have been appointed.

 

P decides to start by firstly decomposing the full scope of the project into a hierarchy of work packages.

 

Secondly P intends to create a structure showing the reporting relationships and communications channels for the entire project team.

 

Thirdly, P  plans to embark on a systematic process of identifying all the individual elements that comprise the total cost of the project in order to calculate a bottom-up budget.

 

Select the structures that P will adopt in the correct order.

Options:

A.

Work Breakdown Structure / Organisation Breakdown Structure / Cost Breakdown Structure


B.

Organisation Breakdown Structure / Work Breakdown Structure / Cost Breakdown Structure


C.

Organisation Breakdown Structure / Cost Breakdown Structure / Work Breakdown Structure


D.

Work Breakdown Structure / Cost Breakdown Structure / Responsibility Assignment Matrix


Expert Solution
Questions # 44:

University Z is about to take on a major project of changing from traditional written examinations to computer-based objective test questons.

 

Y is the systems manager at the university and has been appointed as the Project Manager. The university is very traditional in its management structure, whereby functional specialists manage each department.  However, for this project, Y considers that a matrix structure would be required. The Vice Chancellor is not convinced that a matrix structure would be appropriate.

 

There are a number of advantages of a matrix structure. Which of the following should Y use in his argument to convince the Vice Chancellor that a matrix structure is appropriate?

 

Select ALL that apply. 

Options:

A.

Responsibilities are clearly identified


B.

Decision making is improved


C.

Lateral communications are improved


D.

Reporting lines are clearly established


E.

Managers are exposed to organisation-wide problems


F.

Specialist are able to appraise other disciplines


Expert Solution
Questions # 45:

What is the main use of the Thomas-Kilmann Conflict Mode Instrument?

Options:

A.

It is a framework for assessing the causes of conflict in an organisation.


B.

It is a framework for assessing the symptoms of conflict in an organisation.


C.

It is a framework for classifying different ways of handling conflict.


D.

It is a framework for classifying the types of conflict in an organisation.


Expert Solution
Questions # 46:

Which TWO of the following is the Business Strategy of an organisation mainly concerned with?

Options:

A.

The decision to exit a market.


B.

How a product would be priced in the market place.


C.

The competitiveness of a particular division.


D.

The efficiency of production, marketing and other functions.


E.

Setting the direction for the organisation.


Expert Solution
Questions # 47:

Harvey Maylor defined four stages in the life cycle of a project. This became known as the 4D model.

Match the correct stage to each activity.

Question # 47


Expert Solution
Questions # 48:

Which of the following best describes the resource based view of strategy?

Options:

A.

Carrying out a SWOT analysis to set strategy.


B.

Recognising that competitive advantage stems from some unique asset or competence possessed by the organisation.


C.

Recognising competitive advantage stems from scanning the environment.


D.

Setting a strategy by creating the conditions for new ideas to flourish.


Expert Solution
Questions # 49:

The concept of core competences is key to successful outsourcing strategy. Organisations should:

Options:

A.

focus on core competences and outsource non-core competences to external firms that can add more value.


B.

focus on non-core competences in order to drive down the cost of non value adding activities.


C.

focus on core competences by outsourcing these functions to external firms that can add more value.


D.

focus on non-core competences by applying transaction cost theory to external firms.


Expert Solution
Questions # 50:

Staff in Company A are sceptical that the new IT system being purchased will be properly implemented.

 

Which of the change management options below should management use to break down the resistance against the new system?

Options:

A.

Coercion


B.

Participation


C.

Manipulation


D.

Facilitation


Expert Solution
Viewing page 5 out of 7 pages
Viewing questions 41-50 out of questions