E2 Exam Topic 5 Question 41 Discussion:
Question #: 41
Topic #: 5

In the model of the organisational iceberg, which of the following is NOT one of the hidden elements?


A.

Communication pattern


B.

Feelings


C.

Style


D.

Structure