E2 Exam Topic 5 Question 43 Discussion:
Question #: 43
Topic #: 5

P is an experienced engineer and project manager that has just been appointed to manage a complex multi-million pound engineering project. It is the start-up stage of the project and nothing at all has been done so far except for the design work. No other team members have been appointed.

 

P decides to start by firstly decomposing the full scope of the project into a hierarchy of work packages.

 

Secondly P intends to create a structure showing the reporting relationships and communications channels for the entire project team.

 

Thirdly, P  plans to embark on a systematic process of identifying all the individual elements that comprise the total cost of the project in order to calculate a bottom-up budget.

 

Select the structures that P will adopt in the correct order.


A.

Work Breakdown Structure / Organisation Breakdown Structure / Cost Breakdown Structure


B.

Organisation Breakdown Structure / Work Breakdown Structure / Cost Breakdown Structure


C.

Organisation Breakdown Structure / Cost Breakdown Structure / Work Breakdown Structure


D.

Work Breakdown Structure / Cost Breakdown Structure / Responsibility Assignment Matrix