Questions # 21:

An IT program manager is concerned that a program is not achieving its defined incremental benefits due to a lack of delivery by the business team. The IT team has several dependencies on the business team throughout the program. However the business team does not report to the IT program manager and only two business team resources with the appropriate skills are available to complete the required program tasks.

To address this issue, what should the IT program manager do next?

Options:

A.

Schedule a meeting with the business team to discuss transferring the two business team resources to the IT team, update the program risk register to include risk mitigation steps


B.

Escalate the lack of commitment by the business team to the program steering committee: hire a new project resource to complete the required tasks; update the program risk register to Include risk mitigation steps


C.

Review and clarify the business team's program roles and responsibilities determine the schedule impact on benefits Delivery direct the IT project manager to meet with the business team to ensure dependencies are understood and that the appropriate resources can be made available.


D.

Modify the program milestone dates to include a larger contingency, determine the impact on the project implementation date, and update the benefits management plan


Expert Solution
Questions # 22:

66-style connecting blocks (certain designs) can support up to what category of transmission performance?

Options:

A.

Category 3


B.

Category 5


C.

Category 5e


D.

Category 6


E.

Category 6A


Expert Solution
Questions # 23:

Exhibit:

Question # 23

In this future marina layout, what would be the pre-cabling guideline to follow for the terminal A?

Options:

A.

Place distribution cable onto the dock and terminate in a suitable cabinet or enclosure. Run service drop to each boat slip.


B.

Provide one or two pair cables from the boat slips to a distribution terminal on the closest point of land.


C.

Pre-cable each boat slip during construction.


D.

For security, each run should be terminated in the patch panel/ cross-connect at the dockmaster or marina office.


Expert Solution
Questions # 24:

When designing cable tray pathways under an access floor, what is the MINIMUM free space that should exist between the top of the cable tray side rails and the underside of the stringers?

Options:

A.

25 mm (1 in)


B.

51 mm (2 in)


C.

71 mm (3 in)


D.

101.60 mm (4 in)


Expert Solution
Questions # 25:

A program manager is working on benefits. The program team created and updated a benefits register earlier in the program. The benefits register should include which of the following?

Options:

A.

List of planned benefits, earned value (EV) and responsible person


B.

List of planned benefits, measurement method, and component mapping


C.

List of planned benefits, benefit creator and realization date


D.

List of planned benefits, stakeholders, and risk level


Expert Solution
Questions # 26:

Open RFI's should be reviewed on a _________basis.

Options:

A.

daily


B.

bi-weekly


C.

weekly


D.

bi-monthly


Expert Solution
Questions # 27:

An RFQ usually provides more detail than RFP in selection material such as

Options:

A.

delivery date


B.

color


C.

make


D.

mounting option


Expert Solution
Questions # 28:

A program is developing a next-gene ration product line, and one component has been delivered. However, due to a change request, expectations for another component are unmet

What activity should the program manager perform next?

Options:

A.

Program delivery management


B.

Resource Interdependency management


C.

Program performance monitoring and controlling


D.

Benefits sustainment and program transition


Expert Solution
Questions # 29:

A program manager has been assigned to a program that has received approval of the program charter and for which a stakeholder register has been prepared. During stakeholder engagement planning the program manager should consider which of the following stakeholder aspects?

Options:

A.

Attitude about the program external political position and technical expertise


B.

Level of influence and participation and attitude about the program


C.

Expectation of program benefits, level of influence, and organizational culture


D.

Level of support/opposition technical expertise, and organizational culture


Expert Solution
Questions # 30:

What is a passive optical network (PON)?

Options:

A.

A point-to-multipoint network architecture in which unpowered optical splitters are used to enable a single optical fiber strand to serve multiple end-points.


B.

A point-to-point network architecture in which powered optical splitters are used to enable a single optical fiber strand to serve multiple end-points.


C.

A point-to-point network architecture in which unpowered optical splitters are used to enable a single optical fiber strand to serve multiple end-points.


D.

A point-to-multipoint network architecture in which powered optical splitters are used to enable a single optical fiber strand to serve multiple end-points.


Expert Solution