Questions # 71:

A company CEO meets with key customers to learn how they can be better served Alter discovering that some executive team members disagree with each other, the CEO asks the program management office (PWO) to develop a program to better serve key customers based on their strategic importance to the company's long-term goals.

What should the program manager do to establish and successfully manage the program's direction?

Options:

A.

Create a program strategy to obtain the required funding from the portfolio decision team


B.

Develop and foster relationships with stakeholders to improve communication


C.

Conduct stakeholder interviews to address their concerns and expectations


D.

Identify a list of projects, and then assign them suitable project managers


Expert Solution
Questions # 72:

A program completes all component projects and all identified benefits are being delivered However, the program sponsor is concerned that long-term benefits may not meet organizational performance parameters

To ensure the realization of long-term benefits what should the program manager use?

Options:

A.

Benefits register


B.

Benefits sustainment plan


C.

Benefits management plan


D.

Benefits transition plan


Expert Solution
Questions # 73:

After new private equity owners acquire an enterprise, they want to improve its value by reducing costs A new program will restructure the enterprise, including an aging headquarters campus where the main data center is housed A strategic component project presents significant risk to organizational objectives due to Its complexity and dependencies on external parties. After a series of board meetings, the enterprise's investment committee approves a budget to Implement this component project, which will move the old data center from the aging headquarters campus into a new colocation facility Implementation of this component project may now begin, but is already one month behind schedule The program manager now perceives significantly more risk to the larger program due to this delay.

What should the program manager do to address this risk with the program sponsor and governance board?

Options:

A.

Share the concerns with the program sponsor to confirm understanding of the new development Next, update the program budget, implementation plan, and risk management plan for governance board approval


B.

Update the component project's risk register, issue log, implementation plan, and risk management plan next, meet with the program sponsor to revise the program budget. Implementation plan, and risk management plan for governance board approval


C.

Revise the program budget and Implement the component project by managing It closely to recover the month-long delay Next, update the component's project and risk management plans for governance board approval


D.

Update the program budget, and task the component project manager with implementing the plan next, submit a change order for approval to apply more resources to reduce the larger program's risk profile


Expert Solution
Questions # 74:

Component project managers create project management plans for all component projects in a program. The program manager notices that some project managers prefer one status report template while others prefer another

How should the program manager decide which template is appropriate?

Options:

A.

Review the issue with the program management office (PMO) to determine which template to use


B.

Review the issue with the project managers and come to mutual agreement on which template to use


C.

Meet with the program governance board to select an appropriate template


D.

Allow the component project managers to use their preferred templates


Expert Solution
Questions # 75:

A program manager initiates a developmental program. Significant resources and funding are required (or early activities until the program cost and budget estimates are complete

What should the program manager do to understand the financial environment?

Options:

A.

Map costs to the expected benefits realization


B.

Establish intermediate budget based on historical information


C.

Establish program financial framework


D.

Obtain intermediate funding from the executive sponsor


Expert Solution
Questions # 76:

The program manager has a global program with live component projects. The program sponsor wants the management plans, processes/procedures and technology to be uniform across the program. The requirements will create issues and result in increased costs. The program sponsor is new and has imposed these new requirements six months into a three-year program.

What should the program manager do next?

Options:

A.

Accept what the program sponsor requires and implement the changes


B.

Discuss the proposed changes with the stakeholders and project managers, and give the program sponsor Die best option


C.

Respond to the program sponsor if the program sponsor asks about It a second time


D.

Present the risks and benefits of the changes to the program sponsor


Expert Solution
Questions # 77:

For a backbone distribution system serving a usable floor space of ≈ 8,920 m2 (96,000 ft2), the MINIMUM slot area to be used for this back bone is

Options:

A.

≈ 0.040 m2 (60 in2)


B.

≈ 0.048 m2 (72 in2)


C.

≈ 0.056 m2 (84 in2)


D.

≈ 0.064 m2 (96 in2)


Expert Solution
Questions # 78:

Stakeholders ask the program manager to assess reasons for the project's delay and provide a report also, the program manager must identify steps to be taken to ensure the program will finish on time and within budget

The program manager distributes information in accordance with which of the following?

Options:

A.

Stakeholder engagement plan


B.

Program governance charter


C.

Schedule management plan


D.

Communications management plan


Expert Solution
Questions # 79:

Using an earth ground resistance tester, what is the recommended MAXIMUM value for resistance between any two points along the entire length of a bonding or grounding conductor (not including the earth electrode system)?

Options:

A.

0.10 ohm


B.

0.25 ohm


C.

0.50 ohm


D.

1 ohm


E.

2 ohms


Expert Solution
Questions # 80:

When estimating an ICT distribution designer project timeline schedule based on the scope of work which two scheduling methods use network diagrams lo integrate logical activities and identify critical paths on the project? (Select two options.)

Options:

A.

If This Then That (IFTT)


B.

Gantt Chart


C.

Work Breakdown Structure (WBS)


D.

Critical Path Method (CPM)


E.

Program Evaluation Review Technique (PERT)