BICSI Registered Communications Distribution Designer – RCDDv14.1 RCDDv14.1 Question # 80 Topic 9 Discussion

BICSI Registered Communications Distribution Designer – RCDDv14.1 RCDDv14.1 Question # 80 Topic 9 Discussion

RCDDv14.1 Exam Topic 9 Question 80 Discussion:
Question #: 80
Topic #: 9

When estimating an ICT distribution designer project timeline schedule based on the scope of work which two scheduling methods use network diagrams lo integrate logical activities and identify critical paths on the project? (Select two options.)


A.

If This Then That (IFTT)


B.

Gantt Chart


C.

Work Breakdown Structure (WBS)


D.

Critical Path Method (CPM)


E.

Program Evaluation Review Technique (PERT)


Get Premium RCDDv14.1 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.