The program manager completed the program's benefits analysis and planning activities. What will this ensure tor the program?


A.

Information necessary to establish key benefit performance indicators


B.

A transition plan to facilitate the ongoing realization of benefits


C.

A plan to monitor performance due to operational, financial, and benefits changes


D.

A benefits management plan to guide the work through the remainder of the program