Questions # 1:

When designing horizontal pathways, the ICT distribution designer should consider the design's ability to (Select two options.)

Options:

A.

handle only the day one needs as the future is unknown.


B.

minimize occupant disruption when horizontal pathways are accessed.


C.

handle at least 3 different cabling media types.


D.

accommodate cabling changes


E.

accommodate at least 50 percent future growth


Expert Solution
Questions # 2:

A program manager for an electronic gaming manufacturer is managing a new virtual reality program. An international trade agreement in the final stages of renegotiation will reduce supply-chain costs and delivery intervals A materials supplier informs the program manager that when this agreement is finalized, it will shorten the products delivery time.

What should the program manager update first?

Options:

A.

Procurement management plan


B.

Benefits register


C.

Risk register


D.

Benefits management plan


Expert Solution
Questions # 3:

A program manager assigns project managers lo five component projects and continues to develop the program team. Which of the following represents the program manager's strategy?

Options:

A.

Rotate the responsibility for risk assessment among the program components


B.

Coach the project managers to manage project resources


C.

Cross-train the project managers to share expertise


D.

Prepare the project managers to assume larger roles with more responsibility.


Expert Solution
Questions # 4:

During a program's definition phase, it is determined that the best approach for delivering the programs intended benefits is to supplement corporate resources with the procurement of specific products and services from external suppliers. The program manager should use which of the following to determine and/or document the results of the program procurement planning activity?

Options:

A.

Make of buy decisions, alternatives analyses approach to competition, and best mix of contract types


B.

Requests for proposals (RFPs), proposal evaluation criteria, contract management and best mix of contract types


C.

RFPs. alternatives analyses, approach to competition, and requests for quotes (RFQs)


D.

Make-or-buy decisions, proposal evaluation criteria contract management, and RFQs


Expert Solution
Questions # 5:

A client hired an ICT distribution designer who is designing some additional capacity for a customer owned aerial outside plant. Which of the following would be a PRIMARY consideration?

Options:

A.

Clearances will still be adequate with the added equipment.


B.

That all of the poles on the path are at least Class 3.


C.

Sufficient space exists to install additional guying if required.


D.

Utility coordination with public utilities verifies minimum inductive interference.


Expert Solution
Questions # 6:

In a RFI, an ICT distribution designer instructs the contractor to test all the fibers In a PON Installation. Which of the following testing requirements does the designer include?

Options:

A.

Uni-directional 850 nm and 1300 nm


B.

Bi-directional 850 nm and 1300 nm


C.

Uni-directional 1310 nm and 1550 nm


D.

Bi-directional 1310 nm and 1550 nm


Expert Solution
Questions # 7:

A program manager is responsible for constructing a USS50 million building Management suggests it will take three years to complete The program manager can select a design-build option to optimize the construction schedule to 1 5 years However heavy demand for steel is causing price increases and delivery delays. II this trend continues, it could take as long as 4.5 years to complete construction. You learn that a new technology can yield a definitive delivery schedule of 1 25 years

What is the expected time of delivery?

Options:

A.

1.25 years


B.

1 50 years


C.

175 years


D.

1 00 years


Expert Solution
Questions # 8:

The size and number of conduits or sleeves used for backbone pathways depend on the usable floor space served by the backbone distribution system. What is the MINIMUM trade size of sleeves recommended to serve a TR, ER, or EF?

Options:

A.

2


B.

4


C.

6


D.

8


Expert Solution
Questions # 9:

Based on the estimated work area size, what is the MAXIMUM number of work areas that a telecommunications enclosure shall serve?

Options:

A.

20


B.

26


C.

32


D.

36


E.

40


Expert Solution
Questions # 10:

An ICT distribution designer is representing a client during a project execution. What is the designer's role in the Vendor and Contractor Coordination?

Options:

A.

Oversee the sequence of the work and ensure that the job proceeds as anticipated in accordance with the project execution schedule


B.

Synchronizes the daily activities of all trades through daily or weekly meetings (depending on project size, complexity, or criticality) with individual trade PMs. Fore people, supervisors and designers as necessary


C.

Holds two critical meetings to begin the project and allow all parties to introduce themselves

The first meeting usually is conducted with the owner and design team, and the second meeting is with the field personnel and subcontractors


D.

lf specific questions arise regarding coordination of the installation with structural, architectural, and site conditions and work between trades, submit RFIs to the GC with appropriate documentation to demonstrate the concern along with the proposed installation.


Expert Solution