After meeting with the program sponsor and stakeholders, the program manager is asked by the sponsor to accelerate the program to replace two legacy financial systems. The legacy systems are at risk of premature failure.
What should the program manager do next?
A program stakeholder is concerned about information they receive about a project. Who is responsible for reviewing the communications management plan to assure adequate information is provided to the stakeholder'?
A component project manager escalates an issue regarding a key stakeholder to the program manager. The key stakeholder does not respond to emails or phone calls and the project manager believes this key stakeholder is exhibiting a negative attitude toward the work. The key stakeholder has a significant influence over the component project which could impact other components if delays occur. The program manager's attempts to reach the stakeholder via email also fail.
What should the program manager do next?
For a six story building (plus a basement) each of the six floors has a useable area of =3716 m2 (40.000 ft2) There are two riser systems, each serving halt of the useable area on each Moor What are the sleeves quantity and configuration required from fifth floor to sixth floor?
To properly size and provide accurate cost estimates for a communications distribution horizontal pathway that will include BAS system infrastructure, the designer should provide ________ for every BAS outlet or device based on total floor area.
The risk manager completes risk response planning. The risk manager believes that to effectively address all eventualities, an additional action is required.
What should the program manager do next?
A program management team is invited to a company's annual strategy planning session The CEO discusses the mission and vision of the organization, and how the strategic plan will create opportunities to fulfill them
How can the program manager use the company's vision to establish a program?
In a transformational program, all projects are on track and delivering their objective. However stakeholders are hesitant to take on the new processes because performance in the current environment may not be representative of actual performance Stakeholders fear that the program will fail to provide the service required.
To assure positive performance in the current environment, the program manager should do which of the following?
Which of the following is a common application for exothermic welding of earthing (grounding) and bonding conductors?
An ICT distribution designer is preparing a price quote for a building design with multiple floors originally sized at 40.000 ft (3716 m2). While the designer is preparing the quote, the structural engineer indicates the building has been increased in size to accommodate an additional 40,000 ft2 (3716 m3) per floor. The designer's recommendation to the engineer will be to increase the slot area by_____for each additional 40,000 ft3 (3716 m2)