BICSI Registered Communications Distribution Designer – RCDDv14.1 RCDDv14.1 Question # 28 Topic 3 Discussion

BICSI Registered Communications Distribution Designer – RCDDv14.1 RCDDv14.1 Question # 28 Topic 3 Discussion

RCDDv14.1 Exam Topic 3 Question 28 Discussion:
Question #: 28
Topic #: 3

A program is developing a next-gene ration product line, and one component has been delivered. However, due to a change request, expectations for another component are unmet

What activity should the program manager perform next?


A.

Program delivery management


B.

Resource Interdependency management


C.

Program performance monitoring and controlling


D.

Benefits sustainment and program transition