Questions # 71:

A conduit run is installed from the ER to a TR. It has two (2) 90 degree bend and a length of 20 m (65 ft). What will be the MINIMUM test rating of the pull cord left in the conduit?

Options:

A.

20 kg (44 lb)


B.

40 kg (88 lb)


C.

60 kg (132 lb)


D.

90 kg (200 lb)


E.

100 kg (220 lb)


Expert Solution
Questions # 72:

The standard floor space coverage area for each building automation system (BAS), is a BAS outlet or device for every_______ of floor space.

Options:

A.

9.3 m 2 (100 ft 2)


B.

23 m 2 (250 ft 2)


C.

31 m 2 (330 ft 2)


D.

56 m 2 (600 ft 2)


E.

84 m 2 (904 ft 2)


Expert Solution
Questions # 73:

When placing an optical fiber cable in the horizontal optical fiber cabling subsystem, what is the MAXIMUM number of splices that can be used?

Options:

A.

1


B.

2


C.

3


D.

4


E.

5


Expert Solution
Questions # 74:

You are designing a horizontal pathway system where you will provide 100 mm (4 in) conduit and pull boxes. The building architectural elements will only allow for a single layer of conduits (not stacked). The main horizontal pathway system consists of five 100 mm (4 in) conduits. Large single sheath copper cables are not expected to be placed. Which of the following is the MINIMUM width pull box that is to be provided?

Options:

A.

600 mm (24 in)


B.

900 mm (36 in)


C.

1220 mm (48 in)


D.

1520 mm (60 in)


E.

1830 mm (72 in)


Expert Solution
Questions # 75:

Which of the following is true when describing slip sleeves or gutters?

Options:

A.

More costly than pull boxes


B.

Can be used as a splice location


C.

Provides more space for pulling


D.

Cannot be used in place of a pull box


E.

Must be equal in size to the main conduit


Expert Solution
Questions # 76:

Which area of project management covers the blending of various subteams into a project organization with a cohesive plan?

Options:

A.

Integration management


B.

Human resources management


C.

Risk management


D.

Communications management


Expert Solution
Questions # 77:

What is the PERT estimate of time for cable placement on a given job?

- Optimistic time is 100 hours

- Most likely time is 125 hours

- Pessimistic time is 210 hours

Options:

A.

100 hours


B.

125 hours


C.

135 hours


D.

155 hours


E.

175 hours


Expert Solution
Questions # 78:

Select the appropriate task to complete section 2.2 of the work breakdown structure (WBS) below:

2 Technician

2.1 Install cabling

2.2 __________

2.3 Activate wireless

Options:

A.

Install access point


B.

Clean work area


C.

Install pathway for cabling


D.

Confirm wireless coverage


Expert Solution
Questions # 79:

Between the late 60’s and until 1984, what was the service that was to help architects and engineers better design and implement pathways and spaces in commercial buildings for telephone communications?

Options:

A.

BICS


B.

AT&T


C.

CREDFACS


D.

GTE


E.

BICSI


Expert Solution
Questions # 80:

At the end of the second week of a project, the earned value (EV) of work is $8000 USd and the planned value (PV) of work is $7000 USd. What is true about the project?

Options:

A.

The project is ahead of schedule.


B.

The project is over budget.


C.

The project is behind schedule.


D.

The project is under budget.


Expert Solution