Questions # 41:

For the telecommunications industry, the nominal operating voltage is ________ volts DC.

Options:

A.

+ 24


B.

– 24


C.

+ 48


D.

– 48


Expert Solution
Questions # 42:

The formula for calculating BTUs from electrical power is:

Options:

A.

W x 0.707


B.

W x 1.732


C.

W x 3.1416


D.

W x 3.413


Expert Solution
Questions # 43:

You have been asked to provide a N+1 level of power redundancy in the new equipment room (ER) being designed with a Tier-II power supply. What should you do?

Options:

A.

Provide a UPS that serves all of the equipment in the facility.


B.

Provide two separate UPS units with an automatic power failure transfer to serve entire facility.


C.

Provide two separate UPS units with each one serving half the equipment in the facility.


D.

Provide two separate UPS systems with one serving the entire facility and the second on automatic power failure transfer to serve critical circuits only.


Expert Solution
Questions # 44:

You have been asked to provide a UPS that is always serving the load from its batteries and the electrical supply is used only to recharge the batteries. Which one of the following types of UPS will meet this requirement?

Options:

A.

Off line, standby


B.

Line interactive


C.

Online double conversion


D.

Rotary


E.

Flywheel


Expert Solution
Questions # 45:

A rapid increase in voltage with a duration of half a cycle best describes a(n):

Options:

A.

Swell


B.

Overvoltage


C.

Transient


D.

Frequency variation


Expert Solution
Questions # 46:

You are designing a nurse call system for an assisted care facility. What type of nurse call system would best suit the needs for the facility?

Options:

A.

Audiovisual system


B.

Staff emergency system


C.

Tone/Visual system


D.

Bedside system


Expert Solution
Questions # 47:

Which of the following is an alarm management output system?

Options:

A.

Patient monitoring system


B.

Bed monitoring system


C.

Security system


D.

Wireless telephone system


Expert Solution
Questions # 48:

You are renovating telecommunication rooms that support an acute care facility that has 10,000 sq ft floors. The facility will be adding 15,000 sq ft to each of the floors. What is the MINIMUM additional floor space that you will need to expand the TRs to support the new floor space?

Options:

A.

3 m x 3 m (10 ft x 10 ft)


B.

3.5 m x 4.3 m (11.5 ft x 14 ft)


C.

3.0 m x 4.5 m (10 ft x 15 ft)


D.

6 m x 6 m (20 ft x 20 ft)


Expert Solution
Questions # 49:

The ________ system is an application used for storing and viewing captured digital radiology image files.

Options:

A.

CCU


B.

ICU


C.

DICOM


D.

PACS


Expert Solution
Questions # 50:

How much area of wall space is needed in the telecommunications room (TR) to support a nurse call system?

Options:

A.

1.2m x 1.2 m (4 ft x 4 ft)


B.

1.2m x 2.4 m (4 ft x 8 ft)


C.

2.4 m x 2.4 m (8 ft x 8 ft)


D.

2.4 m x 3.6 m (8 ft x 12 ft)