BICSI Registered Communications Distribution Designer - RCDD RCDD-002 Question # 77 Topic 8 Discussion

BICSI Registered Communications Distribution Designer - RCDD RCDD-002 Question # 77 Topic 8 Discussion

RCDD-002 Exam Topic 8 Question 77 Discussion:
Question #: 77
Topic #: 8

What is the PERT estimate of time for cable placement on a given job?

- Optimistic time is 100 hours

- Most likely time is 125 hours

- Pessimistic time is 210 hours


A.

100 hours


B.

125 hours


C.

135 hours


D.

155 hours


E.

175 hours


Get Premium RCDD-002 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.