BICSI Registered Communications Distribution Designer - RCDD RCDD-002 Question # 80 Topic 9 Discussion

BICSI Registered Communications Distribution Designer - RCDD RCDD-002 Question # 80 Topic 9 Discussion

RCDD-002 Exam Topic 9 Question 80 Discussion:
Question #: 80
Topic #: 9

At the end of the second week of a project, the earned value (EV) of work is $8000 USd and the planned value (PV) of work is $7000 USd. What is true about the project?


A.

The project is ahead of schedule.


B.

The project is over budget.


C.

The project is behind schedule.


D.

The project is under budget.


Get Premium RCDD-002 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.