Questions # 11:

Which of the following is the fundamental difference between finite loading and other capacity planning approaches?

Options:

A.

It is highly dependent on advanced computer software to function effectively.


B.

It is only managed by shop floor supervisors.


C.

It can use historical information to drive decision-making processes.


D.

It considers adjustments to plans based on planned capacity utilization.


Expert Solution
Questions # 12:

Which of the following methods places a replenishment order when the quantity on hand falls below a predetermined level?

Options:

A.

Min-max system


B.

Fixed order quantity


C.

Periodic review


D.

Available-to-promlse (ATP)


Expert Solution
Questions # 13:

The primary purpose for engaging in cycle count activities is to:

Options:

A.

eliminate the need for a traditional physical inventory count.


B.

more frequently reconcile the actual on-hand and system on-hand for items.


C.

smooth out the tasks of counting inventory throughout the fiscal year.


D.

improve material handling processes and reduce or eliminate errors.


Expert Solution
Questions # 14:

The costs provided in the table below are associated with buying a quantity larger than immediately needed. What Is the total landed cost based on this table?

Cost CategoryCost

Custom fees$125

Freight$700

Warehouse rent$200

Matenal cost$500

Options:

A.

$825


B.

$1,325


C.

$1,400


D.

$1,525


Expert Solution
Questions # 15:

The question below is based on the following information:

Question # 15

Work Center 1 has an available capacity of 1,200 hours per month. Which of the following amounts represents the cumulative difference between the required capacity and the available capacity of Months 1 through 3?

Options:

A.

50


B.

150


C.

1.250


D.

3.750


Expert Solution
Questions # 16:

Based on the above table, calculate the mean absolute deviation (MAD).

Question # 16

Options:

A.

-25


B.

6.25


C.

18.75


D.

20


Expert Solution
Questions # 17:

An example of a flexibility metric for an organization Is:

Options:

A.

average batch size.


B.

scrap rate.


C.

percentageof orders delivered late.


D.

cycle time.


Expert Solution
Questions # 18:

A company assembles kits of hand tools after receipt of the order from distributors and uses two-level master scheduling. The appropriate levels of detail for the forecasts that are input to master scheduling would be total number of kits and:

Options:

A.

each unique tool.


B.

percentage of total for each tool.


C.

raw material requirements.


D.

specific kit configurations.


Expert Solution
Questions # 19:

A statistical safety stock calculation would be appropriate for:

Options:

A.

components used in multiple end items.


B.

new products at time of introduction.


C.

end items with stable demand.


D.

supply-constrained raw materials.


Expert Solution
Questions # 20:

A newer automotive supplier has not fully developed its information technology (IT) systems. The supplier has Just received a contract from a large automotive manufacturer which requires the supplier to use electronic data interchange (EDI) transactions for receiving orders, sending advance ship notices (ASNs), and receiving invoice payments. What strategy can the supplier adopt to immediately meet the EDI requirements?

Options:

A.

Select, install, and implement EDI software.


B.

Use current third-party logistics provider (3PL) to handle the EDI transactions.


C.

Claim hardship and ask the automotive manufacturer for a waiver.


D.

Negotiate using email as an alternative with the customer.


Expert Solution