Questions # 11:

As the Sprint Planning progresses, the Developers realize that the workload may be greater

than their capacity to complete the work. Which two are valid actions?

(choose the best two answers)

Options:

A.

Remove or change selected Product Backlog items.


B.

The Developers ensure that the Scrum Team is aware, start the Sprint, andmonitor progress.


C.

Recruit additional Developers before the work can begin.


D.

Cancel the Sprint.


E.

The Developers work overtime during this Sprint.


Expert Solution
Questions # 12:

True or False: A Product Owner with multiple teams working on one product should maintain separate Product Backlogs for each team.

Options:

A.

True


B.

False


Expert Solution
Questions # 13:

True or False: The purpose of a Sprint is to produce a valuable, useful Increment.

Options:

A.

True


B.

False


Expert Solution
Questions # 14:

What is the timebox for the Sprint Planning event?

(choose the best answer)

Options:

A.

Monthly.


B.

Whenever it is done.


C.

8 hours for a one-month Sprint.


D.

4 hours for a one-month Sprint.


Expert Solution
Questions # 15:

Who owns the Sprint Backlog?

(choose the best answer)

Options:

A.

The Scrum Master.


B.

The Scrum Team.


C.

The Product Owner.


D.

The Developers.


Expert Solution
Questions # 16:

What does it mean for a Scrum Team to be cross-functional?

(choose the best answer)

Options:

A.

The Scrum Team includes not only developers but also business analysts, architects,and testers.


B.

The Scrum Team includes skilled individuals who together have all the skillsnecessary to create value each Sprint.


C.

Developers on the Scrum Team work closely with business analysts, architects,developers, and testers who are not on the team.


D.

The Scrum Team is a virtual team drawing from separate teams of business analysts,architects, developers, and testers.


Expert Solution
Questions # 17:

During a Sprint, when is new work or further decomposition of work added to the Sprint

Backlog?

(choose the best answer)

Options:

A.

During the Daily Scrum after the Developers approve it.


B.

When the Scrum Master has time to enter it.


C.

When the Product Owner identifies new work.


D.

As soon as possible after it is identified.


Expert Solution
Questions # 18:

When Developers are having trouble delivering an Increment because they do not understand a

functional requirement, what should they do?

(choose the best answer)

Options:

A.

Partially complete the functionality, and discuss the remaining work at the SprintReview.


B.

Add a specialist to the Development Team.


C.

Collaborate with the Product Owner to determine what is possible and acceptable.


D.

Defer the work to a more appropriate Sprint.


Expert Solution
Questions # 19:

What is the accountability of the Product Owner during Sprint 0?

(choose the best answer)

Options:

A.

Determine the composition of the Scrum Team to meet the release plan.


B.

There is no such thing as Sprint 0.


C.

Create the overall release plan to ensure that organizational goals are met.


D.

Make sure enough Product Backlog items are refined to fill the first 3 Sprints.


E.

Gathering, eliciting, and analyzing the requirements to build the Product Backlog.


Expert Solution
Questions # 20:

In accordance with Scrum theory, how should a group of 100 people be divided into multiple

Scrum Teams?

(choose the best answer)

Options:

A.

Create a matrix of skills, seniority, and level of experience to assign people to teams.


B.

Check with the allocation department to see who has worked together before and make these the first teams.


C.

Understanding the product, the product vision and the rules of the Scrum framework, the people divide themselves into teams.


D.

It does not really matter since you can rotate the teams every Sprint to spread knowledge.


Expert Solution