According to the Scrum Guide1, the Developers are responsible for selecting the amount of work they can do in a Sprint, based on their capacity and past performance2. If they realize that the workload may be greater than their capacity, they can either remove or change some of the selected Product Backlog items, or they can start the Sprint and monitor the progress, making adjustments as needed3. Recruiting additional Developers, canceling the Sprint, or working overtime are not valid actions, as they would disrupt the Scrum values of commitment, focus, and respect