Scrum Professional Scrum Product Owner (PSPO I) Exam PSPO-I Question # 11 Topic 2 Discussion

Scrum Professional Scrum Product Owner (PSPO I) Exam PSPO-I Question # 11 Topic 2 Discussion

PSPO-I Exam Topic 2 Question 11 Discussion:
Question #: 11
Topic #: 2

As the Sprint Planning progresses, the Developers realize that the workload may be greater

than their capacity to complete the work. Which two are valid actions?

(choose the best two answers)


A.

Remove or change selected Product Backlog items.


B.

The Developers ensure that the Scrum Team is aware, start the Sprint, andmonitor progress.


C.

Recruit additional Developers before the work can begin.


D.

Cancel the Sprint.


E.

The Developers work overtime during this Sprint.