Questions # 1:

How much work is required of the Developers to complete a Product Backlog item selected during the Sprint Planning?

(choose the best answer)

Options:

A.

As much as they can fit into the Sprint, with remaining work deferred to the next Sprint.


B.

As much as is required to meet the Scrum Team's Definition of Done.


C.

All development work and at least some testing.


D.

A proportional amount of time on analysis, design, development, and testing.


Expert Solution
Questions # 2:

In order to maximize the value of the product, a Product Owner needs awareness of the following: (choose the best answer)

Options:

A.

Competitive research.


B.

Customer feedback.


C.

Product vision.


D.

Forecasting & feasibility.


E.

All of the above.


F.

None of the above.


Expert Solution
Questions # 3:

If Product Backlog refinement is needed, when is the ideal time for refinement to take place and

who should participate?

(choose the best two answers)

Options:

A.

The Scrum Team during the current Sprint, if they have been unable during

preceding Sprints to define Product Backlog items with enough precision to

begin work.


B.

Business analysts in the organization should do this work for the Scrum Team 1- 2 Sprints ahead of the development Sprints.


C.

The Product Owner must do this as essential work in Sprint O.


D.

The Product Owner takes the time between the end of one Sprint and the start

of the next Sprint to complete refinement.


E.

The Scrum Team on an ongoing basis, defining Product Backlog items into

smaller more precise items that are ready for selection.


Expert Solution
Questions # 4:

True or False: A Product Owner should measure product value by the increase in the team's velocity.

Options:

A.

True


B.

False


Expert Solution
Questions # 5:

Who is on the Scrum Team?

(choose all that apply)

Options:

A.

Scrum Master.


B.

Product Owner.


C.

Developers.


D.

Project Manager.


E.

None of the above.


Expert Solution
Questions # 6:

True or False: Product Owners must specify complete acceptance criteria for a Product

Backlog item before the Developers can select the item in Sprint Planning.

Options:

A.

True


B.

False


Expert Solution
Questions # 7:

What typically happens if the Product Backlog is not sufficiently clear at Sprint Planning?

(choose the best answer)

Options:

A.

The Product Owner should select the Sprint Goal for the Scrum Team so that work can begin.


B.

The Developers will find it difficult to create a Sprint forecast they are confident they can meet.


C.

Nothing in particular.


D.

The Scrum Master should not allow this to happen. Look for a new Scrum Master and re-start the Sprint.


E.

Sprint Planning is canceled so refinement can be done first.


Expert Solution
Questions # 8:

Which of these may a Scrum Team deliver at the end of a Sprint?

(choose the best answer)

Options:

A.

Failing unit tests, to identify acceptance tests for the next Sprint.


B.

A single document, if that is what management asked for.


C.

An Increment of software with minor known bugs in it.


D.

A valuable, useful Increment that meets the Definition of Done.


Expert Solution
Questions # 9:

What is the typical size for a Scrum Team?

(choose the best answer)

Options:

A.

At least 7.


B.

9.


C.

10 or fewer.


D.

7 plus or minus 3.


Expert Solution
Questions # 10:

True or False: The Sprint Backlog is a result of Sprint Planning, and it includes the Sprint Goal.

Options:

A.

True


B.

False


Expert Solution