PSPO-I Exam Topic 1 Question 1 Discussion:
Question #: 1
Topic #: 1

How much work is required of the Developers to complete a Product Backlog item selected during the Sprint Planning?

(choose the best answer)


A.

As much as they can fit into the Sprint, with remaining work deferred to the next Sprint.


B.

As much as is required to meet the Scrum Team's Definition of Done.


C.

All development work and at least some testing.


D.

A proportional amount of time on analysis, design, development, and testing.