Scrum Professional Scrum Product Owner (PSPO I) Exam PSPO-I Question # 15 Topic 2 Discussion

Scrum Professional Scrum Product Owner (PSPO I) Exam PSPO-I Question # 15 Topic 2 Discussion

PSPO-I Exam Topic 2 Question 15 Discussion:
Question #: 15
Topic #: 2

A Project Manager working with your Scrum Team has raised concerns about progress and money spent. What are the two best responses?

(choose the best two answers)


A.

Promote transparency by sharing the Product Backlog and ensuring the Project

Manager has access.


B.

Have a discussion with the Project Manager; share the current impediments and

forecast for the Sprint.


C.

Show the Earned Value Analysis (EVA) report.


D.

Scrum does not have Project Managers so disregard their concerns.


E.

Share the last stakeholder briefing document prepared by the Product Owner.


Get Premium PSPO-I Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.