Questions # 1:

Which is the BEST method of communication to gather feedback?

Options:

A.

Receiving emailed diagrams to encourage discussion


B.

Conducting online surveys to obtain a range of opinions


C.

Meeting face-to-face to encourage an exchange of views


D.

Discussing over the telephone to gather feedback quickly from stakeholders


Expert Solution
Questions # 2:

How does PRINCE2 Agile describe Scrum?

Options:

A.

Scrum is an IT method


B.

Scrum is agile and agile is Scrum


C.

Scrum is the most well-known agile framework


D.

Scrum is a project management framework


Expert Solution
Questions # 3:

Which practice has the purpose of controlling uncertainties that would affect the project’s objectives?

Options:

A.

Plans


B.

Issues


C.

Quality


D.

Risk


Expert Solution
Questions # 4:

Which principle ensures that people are empowered to self-manage and stay in control with the appropriate level of governance?

Options:

A.

Ensure continued business justification


B.

Tailor to suit the project


C.

Manage by exception


D.

Focus on products


Expert Solution
Questions # 5:

Which statement about the ‘embrace change’ target is CORRECT?

Options:

A.

It re-establishes team dynamics when a new member joins the team


B.

It trades user stories for those of a similar size


C.

It results in the late delivery of the minimum viable product


D.

It degrades the performance of the features that are delivered


Expert Solution
Questions # 6:

What should be emphasized when tailoring the PRINCE2 Progress theme?

Options:

A.

Monitoring what is being delivered


B.

Tracking time and cost


C.

Planning resources


D.

Assessing the impact of risks


Expert Solution
Questions # 7:

Which statement about the ‘accept that the customer doesn't need everything’ target is CORRECT?

Options:

A.

It is achieved by testing only a few features to deliver on time


B.

It is achieved by ensuring that the operational product has complete documentation


C.

It is based on the concept that people generally use a limited number of product features


D.

It enables a more accurate final product to be produced


Expert Solution
Questions # 8:

What does velocity typically measure?

Options:

A.

Work packages completed by the team


B.

The rate of progress the team is making


C.

The number of timeboxes completed


D.

The speed that a minimum viable product is created


Expert Solution
Questions # 9:

Which statement explains the PRINCE2 Agile behavior of ‘exploration’?

Options:

A.

It empowers the project management team at the delivery level


B.

It uses the most effective channel to communicate information


C.

It displays the progress rate to everyone using burn-down charts


D.

It seeks out feedback collaboratively from project stakeholders


Expert Solution
Questions # 10:

Which is a typical characteristic of ‘business as usual’ work?

Options:

A.

It requires a specific dedicated project manager


B.

It is executed by program management


C.

It is delivered by a temporary team


D.

It is delivered by an established team


Expert Solution