Which statement explains the PRINCE2 Agile behavior of ‘exploration’?
It empowers the project management team at the delivery level
It uses the most effective channel to communicate information
It displays the progress rate to everyone using burn-down charts
It seeks out feedback collaboratively from project stakeholders