Questions # 151:

Which of the following is an input to the Direct and Manage Project Execution Process?

Options:

A.

Approved corrective actions


B.

Approved contract documentation


C.

Work performance information


D.

Rejected change requests


Expert Solution
Questions # 152:

What document should be reviewed by a project manager before finalizing the project closure?

Options:

A.

Customer acceptance


B.

Statement of work


C.

Product report


D.

User manual


Expert Solution
Questions # 153:

Analogous Cost Estimating relies on which of the following techniques?

Options:

A.

Expert Judgment


B.

Project Management Software


C.

Vendor Bid Analysis


D.

Reserve Analysis


Expert Solution
Questions # 154:

The degree of risk shared between the buyer and seller is determined by the:

Options:

A.

contract type.


B.

sponsors.


C.

project manager.


D.

stakeholders.


Expert Solution
Questions # 155:

What is the function of a Project Management Office (PMO)?

Options:

A.

To focus on the coordinated planning, prioritization, and execution of projects and subprojects that are tied to the parent organizations' or the client's overall business objectives.


B.

To coordinate and manage the procurement of projects relevant to the parent organization's business objectives and to administer the project charters accordingly.


C.

To administer performance reviews for the project manager and the project team members and to handle any personnel and payroll issues.


D.

To focus on the specified project objectives and to manage the scope, schedule, cost, and quality of the work packages.


Expert Solution
Questions # 156:

Which is a tool or technique used in scope definition?

Options:

A.

Templates, forms and standards


B.

Change requests


C.

Stakeholder analysis


D.

Project assumptions


Expert Solution
Questions # 157:

Which of the following is a conflict resolving technique that emphasizes areas of agreement rather than areas of difference?

Options:

A.

Withdrawing/Avoiding


B.

Forcing


C.

Collaborating


D.

Smoothing/Accommodating


Expert Solution