Which of the following is NOT an MSP Governance Theme?
Significant changes to the customer processes have been delivered and Tranche 2 is now complete. Many engineering staff do not believe that the Training Project is needed in Tranche 3 as they feel the changes to the new customer processes are minor. The programme manager is concerned that the engineering staff may have misunderstood the extent of the changes. As a result, the programme manager noted in the end-of-tranche report for Tranche 2, that there needs to be more engagement with engineering staff during subsequent tranches.
Is this recommendation an appropriate application of the 'evaluate new information' process, and why?
The programme is in the middle of Tranche 2 and a new SRO has been appointed. In order to understand the current status of the programme, the SRO has asked for a health check to be carried out. The health check was not in the assurance plan, and there is no budget available to pay for an external auditor. As a result, the programme manager has agreed with the SRO that a senior member of the portfolio office, who is acting as the programme office lead, should complete the health check instead.
How well does this action by the programme manager apply the ‘assurance' theme, and why?
Which activity from the Smart Meter Programme should be delivered using a continual improvement approach?
Which of the following is not correct about 'Leading change'?
Which of the following is NOT set out by the Programme Brief?
The programme is in the ‘design the outcomes’ process for the first time. The Research and Development Project team has recommended that UU sources an imported next generation smart meter. This is an alternative to the development of the smart meter internally. The imported meter can be fully implemented before the CEO retires in three years' time. However, there is a possibility that this meter could lead to future information security risks.
Is this recommendation an appropriate application of the ‘decisions' theme, and why?
Which of following is NOT part of delivering the capability?
The programme is in the ‘plan progressive delivery' process for the first time and the business case has been confirmed. The programme manager is now attempting to get commitment from the Call Centre Manager that they will provide the staff needed in Tranche 1.
Is this an appropriate application of the ‘plan progressive delivery' process, and why?
Which of following is not expected from senior leadership of programme?