MSP-Practitioner Exam Topic 2 Question 19 Discussion:
Question #: 19
Topic #: 2

The programme is in the ‘plan progressive delivery' process for the first time and the business case has been confirmed. The programme manager is now attempting to get commitment from the Call Centre Manager that they will provide the staff needed in Tranche 1.

Is this an appropriate application of the ‘plan progressive delivery' process, and why?


A.

Yes, because the Call Centre Manager should commit the resources before Tranche 1 begins


B.

Yes, because resources from the call centres will be critical to the success of Tranche 1


C.

No, because the sponsoring group should commit the resources before Tranche 1 begins


D.

No, because resources should be appointed by the project management team when Tranche 1 begins