The programme is in the ‘plan progressive delivery' process for the first time and the business case has been confirmed. The programme manager is now attempting to get commitment from the Call Centre Manager that they will provide the staff needed in Tranche 1.
Is this an appropriate application of the ‘plan progressive delivery' process, and why?