PeopleCert MSP Practitioner, 5th edition Exam MSP-Practitioner Question # 17 Topic 2 Discussion

PeopleCert MSP Practitioner, 5th edition Exam MSP-Practitioner Question # 17 Topic 2 Discussion

MSP-Practitioner Exam Topic 2 Question 17 Discussion:
Question #: 17
Topic #: 2

The programme is in the ‘design the outcomes’ process for the first time. The Research and Development Project team has recommended that UU sources an imported next generation smart meter. This is an alternative to the development of the smart meter internally. The imported meter can be fully implemented before the CEO retires in three years' time. However, there is a possibility that this meter could lead to future information security risks.

Is this recommendation an appropriate application of the ‘decisions' theme, and why?


A.

Yes, because the proposed option should gain the CEO’s full support


B.

Yes, because providing a clear recommendation should bring pace and value


C.

No, because there are security risks identified with the option proposed


D.

No, because a ‘do-nothing’ option and at least two others should be provided