The programme is in the ‘design the outcomes’ process for the first time. The Research and Development Project team has recommended that UU sources an imported next generation smart meter. This is an alternative to the development of the smart meter internally. The imported meter can be fully implemented before the CEO retires in three years' time. However, there is a possibility that this meter could lead to future information security risks.
Is this recommendation an appropriate application of the ‘decisions' theme, and why?