Significant changes to the customer processes have been delivered and Tranche 2 is now complete. Many engineering staff do not believe that the Training Project is needed in Tranche 3 as they feel the changes to the new customer processes are minor. The programme manager is concerned that the engineering staff may have misunderstood the extent of the changes. As a result, the programme manager noted in the end-of-tranche report for Tranche 2, that there needs to be more engagement with engineering staff during subsequent tranches.
Is this recommendation an appropriate application of the 'evaluate new information' process, and why?