When reviewing the risk profile of an enterprise during the governance design phase, what MUST be established prior to conducting a high-level risk analysis?


A.

Risk response strategy


B.

Key risk indicators (KRIs)


C.

Enterprise's risk appetite


D.

Risk management framework