Questions # 81:

A key stakeholder's requirement contradicts the organization's strategic objectives. The program manager meets with the stakeholder but is unable to reach a compromise on the requirement

What should the program manager do first?

Options:

A.

Meet with the program management office to update the benefits management plan


B.

Meet with the organization's strategic planning committee to obtain clarification


C.

Meet with the program sponsor to address the issue


D.

Meet with the customer to determine if the stakeholder's requirement is valid


Expert Solution
Questions # 82:

In a budding with one join room for serving as the FR and EF and four dedicated TRs on the same floor a total of__________ 103 mm (4 trade size) conduits should be installed to interconnect the backbone pathways to the ER.

Options:

A.

4


B.

8


C.

16


D.

20


Expert Solution
Questions # 83:

A program manager initiates a developmental program. Significant resources and funding are required (or early activities until the program cost and budget estimates are complete

What should the program manager do to understand the financial environment?

Options:

A.

Map costs to the expected benefits realization


B.

Establish intermediate budget based on historical information


C.

Establish program financial framework


D.

Obtain intermediate funding from the executive sponsor


Expert Solution
Questions # 84:

Several issues are identified on one component project in a program During a meeting with that component's project manager, the program manager offers several suggested resolutions Two weeks later, they meet again to review progress The project manager had reviewed the issues and suggested resolutions, but delayed a decision. This two-week delay in taking action caused delays in the project schedule

What should the program manager do?

Options:

A.

Join project-level issue resolution meetings to accelerate the decision-making process.


B.

Initiate discussions with the program governance board about assigning a more experienced project manager to the project


C.

Emphasize that the project manager needs to address the issues and follow up at the next scheduled meeting


D.

Develop an immediate corrective action plan with the project manager and coach them on decision-making responsibilities


Expert Solution
Questions # 85:

The chief executive officer reminds a program manager that a program must deliver a 30% reduction in customer complaints by the end of the year. Where is this expectation documented1?

Options:

A.

Program quality standards


B.

Customer management plan


C.

Benefits management plan


D.

Benefits sustainment plan


Expert Solution
Questions # 86:

Company A acquires company B. which leads to a two-year program lo integrate the processes and systems Company B uses a different project management process, and the company's staff is unhappy about the acquisition As a result company B's project team fails to provide status and cost data in a format that conforms to the program standards.

What should the program manager do first?

Options:

A.

Inform the stakeholders of this Issue as soon as possible


B.

Change the program standards, aligning them with the project standards


C.

Work with the reports provided to extract the required information


D.

Remind the project manager of the relevant program standards