Questions # 21:

Open RFI's should be reviewed on a _________basis.

Options:

A.

daily


B.

bi-weekly


C.

weekly


D.

bi-monthly


Expert Solution
Questions # 22:

An IT-related program has a critical team in a region experiencing a crisis. Due to uncertainty about the region's changing environment a company's senior leadership asks the program manager to decrease dependencies on the critical team that should the program manager do to mitigate the Impacts of this request?

Options:

A.

Update the procurement management plan, and begin the request for proposal (RFP) process to replace the critical team

by staff augmentation


B.

Meet with the steering committee to request assistance and influence in obtaining additional resources


C.

Level resources, and empower the critical team to complete its work before regional instability impacts its efforts


D.

Revisit the program management plan to clearly identify how decreasing critical team dependencies will impact component projects


Expert Solution
Questions # 23:

A company wants to perform a preliminary stakeholder analysis lo assess a new program's support. What should the program manager develop'?

Options:

A.

Program communications management plan and the stakeholder charter


B.

Responsible accountable consult and inform (RACI) matrix stakeholder list, and escalation process


C.

Stakeholder strengths weaknesses, opportunities and threats (SWOT) analysis


D.

Stakeholder engagement plan, stakeholder register, and stakeholder map


Expert Solution
Questions # 24:

The program manager takes over a poorly performing program After a review of the documentation and interviews with the program sponsor, stakeholders and program constituents, the program manager realizes that the program is not aligned with the corporate/organizational goals. The program manager must realign the constituent protects and components to meet the program's needs

What action should the program manager take to realign the program?

Options:

A.

Assess the program schedule and determine how to maintain all projects and components within the program


B.

Discuss the situation with the program stakeholders and let them decide which projects to accelerate and which to close


C.

Discuss the situation with the program sponsor(s) and let the sponsor(s) make the decision as to which projects to accelerate and which to close


D.

Develop a change request to present to the governance board, accelerate some projects, close some projects and reassign some resources


Expert Solution
Questions # 25:

A small regional utility closes a customer rewards program and transitions it to operations The executive sponsor and program manager are concerned about the impact on benefits realization The program manager assures the executive sponsor that any corrective actions will be included in the next phase.

What should the program manager do to ensure a successful transition?

Options:

A.

Ask each project manager to consolidate and file all program documentation in the corporate archives


B.

Obtain all project managers' contact information, and then have them reassigned back to their functional managers


C.

Ask the program's business analyst to collect all project information and create a report


D.

Ensure that all program documents, including lessons learned are archived in the knowledge repository


Expert Solution
Questions # 26:

Which of the following is TRUE for tele communications spaces?

Options:

A.

Maintain aim (3.28 ft) clearance between equipment and plumbing fixtures such as mop sinks


B.

Plumbing piping not related to the support of the space should not pass through the space.


C.

Relative humidity snail be maintained at 40% ± 5%.


D.

Close proximity to water service is desired so consider locating the ER in the pipe chase.


Expert Solution
Questions # 27:

Which two of the following are ADVANTAGES of aerial pathways? (Select two options.)

Options:

A.

Quick to install


B.

Has a low initial installation cost


C.

Affect the aesthetic appearance of the property


D.

Economical over a long life


E.

Readily accessible for maintenance


Expert Solution
Questions # 28:

Which type of protection for electrical power stations provide isolation against a rise in potential of station ground and also provide drainage protection against longitudinally-induced voltages?

Options:

A.

Isolating transformers


B.

Neutralizing transformers


C.

Mutual drainage reactors


D.

Unit-type neutralizing transformers


E.

2-winding neutralizing transformers


Expert Solution
Questions # 29:

What is the MINIMUM clearance needed between the front of the telephone booth and any wall or fixture for most installations?

Options:

A.

300 mm (12 in)


B.

450 mm (18 in)


C.

610 mm (24 in)


D.

914 mm (36 in)


E.

2.4 m (8 ft)


Expert Solution
Questions # 30:

A program manager building the world's largest cruise ship is resolving the conflict between the two main sponsors who cannot agree on the number of food and beverage outlets to have onboard. What should the program manager do?

Options:

A.

Finalize the business case and market analysis with the cote program team and present the findings to the chief executive officer for approval


B.

Work with the core program team to conduct a market analysis and make the decision based on the best return on investment


C.

Arrange a meeting with both sponsors and the steering committee to present the market analysis and work through the conflict


D.

Engage the program stakeholders present the market analysis and findings to facilitate the decision on the best option